Tuesday, August 26, 2008

Framing - Part V

Framing continues and the roof is starting to take shape. Pilings for the decks will be washed in tomorrow and installation of the windows will start after Labor Day!

Friday, August 22, 2008

Septic System Installed

The septic system is installed and inspected.

Monday, August 18, 2008

Framing - Part IV

Framing continues, with the top floor walls almost complete. The septic tank is scheduled to be installed this week and the roofers should start within the next couple of days.

Tuesday, August 12, 2008

View

That blue stuff on the horizon would be the Atlantic Ocean. This will be our view from the screened in porch.

Thursday, August 7, 2008

Construction Loan / Framing - Part III

We are signing the papers today for our construction loan. Of all the mortgage loans I've completed in my lifetime, this one gets the prize for taking the longest amount of time. Everyone has been very pleasant to work with, but it has been a slow process. Anyway, the latest framing pictures are attached. The weather has been good and excellent progress continues to be made!

Monday, August 4, 2008

Framing - Part Deux

Framing continues, with the first floor platform in place and the walls taking shape!